Quicklinks
TECHNOLOGY
Thank you for visiting the Pine Tree ISD Bond Program Page.
Project Description
Schedule & Dates

Date      Event                        
 3/29/12 
Completed
Phase I of Technology Projects completed: WAN (Wide Area Network) Upgrades to the network that connects our campuses / facilities together.  Project work during phase III are completed by Computer Land of Longview.



   
 
 9/21/12  Phase II of Technology Projects completed: The LAN (Local Area Network) re-cabling of the Junior High School and Intermediate CampusProject work during phase III are completed by Computer Land of Longview.


 


 
 9/21/12 

Phase III of Technology Projects projected to be completed: Upgrading existing Wifi network district wide to increase capacity and speed.  Project work during phase III are completed by Computer Land Network Technologies of Longview.

 
 8/21/12  Deadline for Bidding of Phase IV  
     
 To be
Announced
  Phase IV of Technology Projects projected to be completed:The LAN re-cabling of the High School Campus.  Projects during Phase IV are completed by PBK and Gallagher.

 

The bond website will continue to be updated with the latest information as each project progresses. Submit bond questions or comments to [email protected] or call 903-295-5136.
Architect: PBK Architects, Contact: Fred , AIA, Principal 


Construction Manager at Risk: Gallagher Construction

    
Our mission is to continue a tradition of excellence by providing a high-quality and challenging educational environment, maximizing opportunities for the success of all students, equipping them to become responsible, involved, and productive citizens.

Copyright © 2016 - Pine Tree Independent School District

powered by ezTaskTitanium TM